CUSTOMER SERVICE
ABOUT US
MORE LINKS
|
|
Construction
Locust
Shade Water Storage Tank
Quantico National Cemetery Booster
Station
Service Authority Administration Building Expansion
Montclair South Water Tank
Tank Demolition
Fuller Heights Pump Station “B”
Repaint Bethlehem Road Water Tank
Fuller Heights Road Force Main
Marsteller – Skylark Drive Sewer
System
Linton Hall Sewage Pumping Station
H. L. Mooney Advanced Waste Water Treatment Plant
Upgrade
| Locust Shade Water
Storage Tank |

The
Locust Shade Water Storage Tank will be a 1.6
million-gallon ground-level tank. It will be
located on the Marine Corps Heritage Center
site. The tank will provide operational and
emergency water storage for the Triangle and
Quantico National Cemetery area.
Steelwork
and painting are complete. The access road
is being cut to grade to so that the water
line to the tank can be completed. The tank
is expected to be in operation in late February
2006, with final grading, landscaping, and
fencing to follow shortly. |
| Construction
by Advance Tank and Construction
Company of Pell City, Alabama. |
< Top
| Quantico
National Cemetery Booster Station |
|
The
Quantico National Cemetery Booster Station is being
built to pump water to the National Cemetery, which
is too high to be served by the tanks in the Dumfries-Triangle
Service Level. Its primary purpose is to provide potable
and irrigation water to the Cemetery. It will also
benefit county residents along the route (Forestburg
Lane and Joplin Road) by making potable water available
and providing fire protection.
Mechanical
work is complete. Station controls to be installed
in February. Final completion anticipated in
early spring.
Picture
shows the station. |
| Construction
by ALPHA Construction Company, Inc. of Fort Washington,
Maryland. |
< Top
| Service
Authority Administration Building Expansion |
In
the fall of 2002 the
Service Authority Administration conducted an evaluation
of the Service Authority’s
current and future requirements
for office space in the Spittle Building. This evaluation
determined that
in order to meet the
current space requirements major renovations of the
Spittle Building would be required,
and the most economical
course would be to proceed with construction of an
addition to the building and
renovation of the existing
office area. The addition and renovations would be
designed to meet both current
and future needs. The
original design of the Spittle Building and property
purchased by the Service Authority
anticipated a future
addition.
The
project consists of a new 19,000 square foot two-story
addition to the north of the existing building including,
a new board room, offices, two kitchens, lunch room,
and wellness center, a 1,000 square foot addition to
customer service, renovation of 10,000 square feet
of existing offices, a new roof, and additional parking.
It is designed to accommodate the needs of the Service
Authority to the year 2023.
The
addition is complete. The contractor is working on
the punch list for renovations of the existing building.
The picture (above) shows the addition from the east
side. |
| Construction
by Britt Construction, Inc.
of Chantilly, Virginia. |
< Top
| Montclair
South Water Tank |
The
project consists of the construction of a new 2 million-gallon
hydropillar water storage tank to replace an existing
water tank. The new tank column will house a water
booster station. The tank site is adjacent to Prince
William Forest Park.
Steel
work is nearing completion. Picture shows the
top row of the vertical shell in place. A domed
roof will be installed on top of that. Painting
will begin in spring 2006. Tank completion
anticipated in October 2006. |
Construction
by CB&I Constructors, Inc. of Alpharetta, Georgia. |
< Top
| Tank
Demolition |
In
order to accommodate the significant growth
in Prince William County as well as improve
water pressure and quality, the Prince William
County Service Authority has constructed water
storage tanks to replace obsolete tanks currently
in place. As a result, the PWCSA has recently
undertaken three tank demolition projects,
of which two tanks have been demolished. The
remaining tank (Nob Hill tank), pictured here,
will be demolished after the Locust Shade Tank
is put in service. The Nob Hill tank is one
of the oldest tanks in the Authority’s
system [built in the 1950’s] and one
of the smallest, with a usable volume of just
77,000 gallons. The replacement tank has a
usable volume of 1,000,000 gallons. |
Construction
by All Industrial Services,
Inc. of Youngstown, Ohio. |
< Top
| Fuller
Heights Pump Station “B” |
The
project consists of the construction of a new sewage
lift station to replace an existing station at the
same site. The existing lift station was built in the
1950's and has a pumping capacity of approximately
1,000,000 gallons per day. This project will meet the
growing needs of the area including the new Marine
Corps Heritage Center Museum. The new station will
have a pumping capacity of approximately 2,488,000
gallons per day, expected to meet the system needs
until 2025.
The
new station will have three pumps for redundancy as
well as controls that will monitor station conditions.
The new station will have a brick facade. Site improvements
will be included in the work as well as the demolition
of the old station.
Below
grade construction of the wet well and pump room [dry
pit] floors and walls are nearly complete. Picture
shows steel sheeting that lines the excavation to prevent
cave-ins and wall forms for the pump room. |
Construction
by Pizzagalli Construction
Company of South Burlington, Vermont. |
< Top
| Repaint
Bethlehem Road Water Tank |
The
Bethlehem Road tank is undergoing its first repainting
since being built in 1986. The original paint job had
lasted longer than expected (usually about 12-15 years
for paints of the time), but needed to be replaced.
The paint had also been damaged during installation
of the many antennas on the tank.
The
entire tank has been sand blasted to clean steel and
primed. The exterior has also received the intermediate
coat and some of the final coat. Painting activity
has been stopped for the winter and will resume in
April, when the final coats will be applied inside
and out. Antennas will be reinstalled after painting
is complete.
Pictures
show the tank before repainting and in current condition.
The attachments at the top of the tank are containment
outriggers (temporary) for raising a fabric curtain
when painting the exterior. Temporary antenna masts
are visible around the tank.
|
Construction
by Corfu Contractors,
Inc. of Vienna, Virginia. |
< Top
| Fuller
Heights Road Force Main |
The
Fuller Heights Road Force
Main is about 4,750 feet of 12-inch sanitary sewer
force main. It will replace
the existing Lift
Station “B” discharge
force main to provide for the additional capacity needed
for the new Fuller Heights Pump Station “B”,
now under construction.
Approximately 90 percent of the pipeline has been constructed.
Picture
shows force main installed under other utility lines. |
| Construction
by Martin and Gass, Inc. of Alexandria, Virginia. |
< Top
| Marsteller – Skylark
Drive Sewer System |
The
Marsteller – Skylark Drive sewer system is approximately
5,000 feet of small diameter
pressure sewer. The project
is in Nokesville and
will provide public sewer to existing homes in an area
with
several failed septic
drain fields and soils
not well suited for drain fields.
About
2,000 feet of sewer has been installed and work is
progressing quickly. Picture shows installing 2-inch
diameter sewer main on Skylark Drive. |
Construction
by Finley Asphalt & Sealing, Inc. of Manassas Park,
Virginia. |
< Top
| Linton
Hall Sewage Pumping Station |
This
project will replace the existing Linton Hall Lift
Station with a new and larger capacity station. The
existing station has a capacity of 8.4 million gallons
per day (MGD). It is anticipated that the capacity
of the existing station will be exceeded in the year
2007. The new sewage pumping station will have a capacity
of 28 MGD. It will provide capacity for development
in the area according to the County Comprehensive Plan.
The new pumping station will be built adjacent to the
existing station, after which the old station will
be demolished.
The
contractor is preparing the site for construction and
moving construction trailers in. |
Construction
by Pizzagalli Construction Company of South Burlington,
Vermont. |
< Top
| H.
L. Mooney Advanced Waste Water Treatment Plant
Upgrade |

The H. L. Mooney Water Reclamation
Facility was built in 1979. It has the capacity
to treat 18 million gallons of wastewater per
day.
Construction is under way at the
plant to upgrade the level of treatment for an
improved Chesapeake Bay. The construction program
will be completed by the year 2006 at a cost
of approximately $41 million. The major components
of the upgrade program include:
- Modifications
of all aeration basins to
allow nitrogen removal by
biological processes (nitrification
and denitrification).
- New deep bed
gravity filters for polishing
(high efficiency filtering)
of effluent and nitrogen
removal
- A new operations
support facility for offices,
a training center, and complete
maintenance capabilities
- New pretreatment
facilities for grit removal
and odor control
- Additional
aeration and clarification
tanks to compensate for additional
requirements of nitrogen
removal.
- A new ultra-violet
light disinfection system
prior to discharge of treated
and filtered water to Neabsco
Creek.
Preliminary engineering is also
under way to expand the Plant’s capacity
to 24 MGD and to provide a still higher level
of Nitrogen removal to satisfy new regulations
and the Chesapeake Bay Program. |
|
|
|
ENVIRONMENTAL STEWARDSHIP
Drinking Water and Water Reclamation
Consumer Confidence Reports
Going Green

Chesapeake Bay Watershed
Conservation Tips

Only Tap Water Delivers

For Kids and Teachers
Decrease the Grease!
Conservation House

Before You Put it Down the Drain

Leak Detection
Espanol
RELATED LINKS
Environmental Protection Agency (EPA)
American Water Works Association (AWWA)
Water Environment Federation (WEF)
Miss Utility
|